Weco Projects ASP v Zea Marine Carier GmbH: Court-appointed surveyor’s powers in the light of arbitration.

GAVC - lun, 09/16/2019 - 01:01

Genova’s court ruling in Weco Projects ASP v Zea MArine Carier GmbH is remarkably similar to the Belo Horizonte (Cefetra et al v Ms ‘IDA’ Oetker Schiffahrtsgesellschaft MbH & Co KG et al) ruling at the Court of Rotterdam, which I reviewed here. Transport is of a yacht is the issue, sinking the event, and London arbitration the agreed dispute resolution. What powers do the courts in ordinary still have to order interim measures?

The court could have discussed the arbitration /Brussels Ia interface, as well as Article 35’s provisional measures. Instead, it mentions neither and relies entirely on an Italian Supreme Court precedent as Maurizio Dardani and Luca di Marco review excellently here (many thanks to Maurizio for forwarding me the case). An exciting, and missed opportunity to bring these issues into focus.

Geert.

(Handbook of) EU Private international law, 2nd ed. 2016, Chapter 2, Heading 2.2.15.

 

 

 

Pages

Sites de l’Union Européenne

 

Theme by Danetsoft and Danang Probo Sayekti inspired by Maksimer